Friday, September 21, 2012

Exclusive - Japan, Thailand race to rescue of Myanmar's struggling Dawei

A small port is built for temporary use at a site for a billion dollar industrial estate in Dawei district in Myanmar May10 , 2012. REUTERS/Khettiya Jittapong
A small port is built for temporary use
at a site for a billion dollar industrial
estate in Dawei district in
Myanmar May10 , 2012. REUTERS/Khettiya Jittapong

After months of negotiations and failed promises, a proposed multi-billion dollar Myanmar port and special economic zone that could transform Southeast Asian trade appears back on track.

Thai banks aim to keep the project afloat with short-term loans until an expected Japanese loan of up to $3.2 billion (1.9 billion pounds) can be secured, officials and sources familiar with negotiations told Reuters.

Thailand's largest construction firm, Italian-Thai Development Pcl, signed a deal in 2010 to build a deep-sea port and Special Economic Zone (SEZ) in southern Myanmar's coastal Dawei into Southeast Asia's largest industrial complex.

But the project foundered, as the Thai builder failed to secure $8.5 billion to finance construction of its first phase -- roads, utilities and a port.

Underlining Dawei's strategic importance, Japan and Thailand have since intervened to rescue the project.

"Italian-Thai has had difficulty in mobilizing the funding. So now the Thai government has effectively taken over the project," Thaung Lwin, chairman of the Dawei SEZ told Reuters. "The next step is to invite Japan", which he said is committed to seeing the project succeed.

Since the Thai and Myanmar governments agreed on July 23 to connect Dawei to the Thai port of Laem Chabang, 100 km southeast of Bangkok, Thai banks led by Bangkok Bank and Siam Commercial Bank have arranged a 10 billion baht ($325 million) bridge loan to sustain it for another 8-10 months, Somjet Thinaphong, managing director of the Dawei Development Co, an Ital-Thai unit, told Reuters in an interview.

That loan would be followed by a soft loan from the state-backed Japan Bank for International Cooperation to finance the basic port and road infrastructure needed to push the project forward, he added. A source involved in the negotiations said the soft loan could total $3.2 billion. Thaung Lwin of the Dawei SEZ said he expected Japan to emerge as the project's biggest shareholder.

As the former British colony embarks on its most dramatic changes since a 1962 military coup in what was then Burma, mega-projects like the $50 billion 250 sq km (155 sq mile) Dawei SEZ hint at what lies ahead. Super-highways, steel mills, power plants, shipyards, refineries, pulp and paper mills and a petrochemical complex are part of it, as are two golf courses and a holiday resort.

Road and rail routes could link Dawei to neighbours China, India and other parts of Southeast Asia, allowing cargo to bypass the narrow and congested Strait of Malacca to forge shorter trade routes from the Middle East and Africa to China and Japan. The Association of Southeast Asian Nations (ASEAN), a grouping of 10 countries, hopes Dawei will play an important role in its ambitions for a common market in 2015.

For Japan, a better-connected Southeast Asia makes it easier to sell their products and knit together a vast network of suppliers to Japanese-owned factories and manufacturing plants, which include autos and electronic goods.

"Before the yearend, we will have major progress," Pisanu Suvanajata, Thailand's ambassador to Myanmar, said in an interview with Reuters.

LOCAL ANGER

Just months ago, the project was nearly left for dead, a casualty of simmering local resentment and fragile financial backing. About 30,000 people, mostly impoverished rice, cashew and rubber farmers living in thatch-roof huts, are slated to be moved during 10 years of planned construction.

In the Dawei region, many worry about the potential environmental toll and health risks from a project that would be four times bigger than Thailand's largest industrial estate, Map Ta Phut, where pollution between 1996 and 2009 may have contributed to at least 2,000 cancer-related deaths, according to environmental activists who sought legal action to halt the estate in 2009.

Emboldened by the government's surprise suspension of the $3.6 billion, Chinese-led Myitsone dam project last year after weeks of public outcry, residents have pushed hard against Dawei. In response, the government scrapped plans for a 4,000 megawatt coal plant. That's been replaced by plans for a "clean coal" plant that can generate 400 megawatts, said Thaung Lwin of the Dawei SEZ. So-called clean-coal technology involves capturing carbon dioxide and other toxic emissions, and either storing them deep underground or piping them to oil and gas fields.

"If it is clean coal technology, then we will allow it," he added. "Our president visited Japan and saw the clean coal technology at J-Power Group."

But that may not be enough to pacify local residents. Activists who have organised protests against Dawei say it is unclear what types of companies will set up there. Thaung Lwin said he expected Nippon Steel and petrochemical makers to build factories in Dawei.

Local activists raised a banner this week along a recently built highway from Dawei to Thailand that says: "Stop Building Another Map Ta Phut" in Dawei.

"I wish for the project to continue only if the local people agree to it," said Saw Khu, chairman of a 12-village committee formed to study the project's impact on the area. He says Italian-Thai has not done enough to explain the potential pollution risks from the proposed industrial zone.

His and other villages have poured over maps that show where a proposed oil refinery and petrochemical factory will replace rice fields, cashew and rubber trees and jungle.

CHANGING OWNERSHIP

Once infrastructure is in place, Italian-Thai plans to allocate 17 percent of the complex to heavy industries including steel, petrochemicals and oil. It expects construction of the 400 megawatt plant to take at least four years to set up. Gas and hydropower plant are expected to follow.

The project received a much-needed boost on July 23 when Thai Prime Minister Yingluck Shinawatra and Myanmar President Thein Sein pledged to open three additional border crossings along the Thai-Myanmar frontier to help with security and logistics. Next month, Yingluck and Thein Sein will meet again to discuss further support for Dawei.

Pisanu, the Thai ambassador, said Thailand has served as a go-between for Italian-Thai and the Myanmar government as they renegotiate the 60-year concession signed by Italian-Thai in November 2010 to develop Dawei. Under that deal, Italian-Thai had a controlling 51 percent stake in Dawei Development Corp. Max Myanmar Group, owned by Burmese tycoon Zaw Zaw, had 25 percent. The Myanmar government had the rest.

Italian-Thai said it would remain the biggest shareholder in the first phase of the project, but a new consortium is expected to emerge, with shares held by the Thai, Japanese and Myanmar governments along with some private companies.

"In the consortium, the Japanese government will take some share. For the Myanmar government, the share will be given to Japan," said Thaung Lwin, chairman of the SEZ. "The Japanese government will help get the private sector involved."

Somjet said he expected the share of Zaw Zaw's powerful Max Myanmar to be diluted, but that the full terms are likely to be discussed at the next meeting between the Thai and Myanmar governments, tentatively scheduled for early October.

"Both the Thai and Myanmar governments would heavily get involved in the road-link and port simply because those are public projects and not totally commercial," said Somjet, head of the Dawei Development Co.

"Financially, if governments get involved, they have to help make it a success."-The Star (September 21, 2012)

No comments: